Ground freezing for the construction of four cross-passages - Ismāilia road tunnel

Ismāilia road tunnel

Ground freezing to create four cross-passages

Client

Bauer Group

Location

Under the Suez Canal in Ismāilia, Egypt

Execution period

April 2018

until February 2019

Project details

Scope of work

Technical data at a glance

  • Tunnel diameter 11.30 m clear diameter per tunnel tube
  • Tunnel length 2x4,380 m
  • Length of the cross-passages 12.60 m
  • Depth of the tunnel tubes 35-70 m
  • Freezers used: 4x100 kW active and 2x94 kW as standby
  • Freezer tubes: 40-50 pieces/crosscut
  • Temperature measuring tubes 6 pieces/crosscut

Special features

Soil conditions: Deep and shallow clay, sandstone medium to very dense sand

Our projects
Current & completed work

Drone image of the construction site shaft Großgartach and Kochendorf: major "SuedLink" energy transition project

Grossgartach and Kochendorf: Major energy transition project

Sinking the Grossgartach and Kochendorf shafts for underground routing

Drone image of Woodsmith Mine winding tower construction site

Woodsmith Mine

Construction of three shafts for Woodsmith mine in North Yorkshire, UK

Nezhinsky mine

Sinking two freeze shafts for the Nezhinsky potash mine of OOO Slavkaliy in Belarus

Graphic 3D representation of the Malmberget iron ore mine in Sweden - Underground Sinking Plant

Malmberget iron ore mine

Concept study for sinking two new shafts

Shaft Konrad 2

Rehabilitation and development of the shaft and excavation of connected mine chambers

Uralkali mine Ust-Jaiwa

Sinking two freeze shafts for the Uralkali mine Ust-Jaiwa in Russia